Projects in Parkland

Project Updates in the City of Parkland

ROUNDABOUT: UNIVERSITY DRIVE AND OLD CLUB ROAD

To reduce traffic back-ups that occur at the intersection of University Drive and Old Club Road (the entrance to Parkland Golf and Country Club), a roundabout will be constructed to replace the existing three-way stop intersection. The center of this roundabout, like others in the City of Parkland (Riverside Drive-Holmberg Road and Parkside Drive-Holmberg Road) will be landscaped and have various features. Click here for more information.

MECCA BOULEVARD SIDEWALK

On June 11, 2020, crews began repairing the sidewalk along the west side of Mecca Boulevard from U.S. Highway 441 / State Road 7 to Hillsboro Boulevard. This process will continue for several weeks and result in periodic temporary single lane closures. It is anticipated the impact to traffic will be minimal and not result in substantive delays. This project is expected to be complete in the Fall of 2020.

HILLSBORO BOULEVARD EXTENSION

The Falls at Parkland is a 55 and older community that is under development just west of Parkside Drive and immediately south of Loxahatchee Road.  The developer, Ryan Homes/Parkland Centerline, was required, as a condition of development, to construct an extension of Hillsboro Boulevard that feeds into the Falls at Parkland.  That extension has been completed and runs along the south side of Chabad of Parkland, intersects Parkside Drive at a four-way stop, and continues west into the Falls at Parkland.  Click here for more information.

TRAFFIC SIGNAL:  NOB HILL ROAD - HILLSBORO BOULEVARD

Work is underway on a traffic signal at the intersection of Nob Hill Road and Hillsboro Boulevard and is expected to be completed by the end of Summer of 2020.  For more information on this project, and information on traffic signals in general, click here.

CONSTRUCTION AT UNIVERSITY DRIVE AND HILLSBORO BOULEVARD

Construction of a charter school continues on the northwest corner of the intersection of University Drive and Hillsboro Boulevard.  Foundational work was largely complete at the end of 2019 and crews continue site work as they begin vertical construction of the building after the new year.  This is not a City of Parkland (City) project, but the developer has told the City completion of the project is planned for no later than Fall 2020.  In preparation for the facility opening, the University Drive southbound right turn lane onto Hillsboro Boulevard will be lengthened.  A northbound left turn lane onto Hillsboro Boulevard from University Drive will be added.  On Hillsboro Boulevard, a westbound right turn lane will be added to feed the main entrance of the school on Hillsboro at the west end of the property.  Also, the existing eastbound Hillsboro Boulevard left turn lane into the school will be extended.  This road work began in April 2020 with some lane restrictions expected.  The development of this property will likely move up the time that a traffic signal would be installed at that intersection.  City staff have already been in contact with Broward County on this matter and the design of the traffic signal has been started.

STREET LIGHTING

The City of Parkland adopted a City-wide plan for street lighting in 2013. Since then, the City, along with Florida Power and Light (FPL) and Broward County, has illuminated University Drive from Holmberg Road to Loxahatchee Road and Nob Hill Road from Heron Bay Boulevard to Hillsboro Boulevard. Click here for more information.

LOXAHATCHEE ROAD IMPROVEMENTS

The reconstruction of Loxahatchee Road is a large-scale collaboration between the City of Parkland, Broward County, the Broward Metropolitan Planning Organization (MPO), and the Florida Department of Transportation (FDOT).  The project will span Loxahatchee Road from State Road 7 / U.S. Highway 441 to the water conservation area and, at this time, is expected to begin sometime in 2023. Click here for more information.

RANCHES DRAINAGE

This project would provide a secondary storm water drainage system to allow for drainage during a large rain or storm event.  This  would help alleviate flooding that now occurs in The Ranches after a storm or heavy rain.  The City of Parkland (City) had a survey conducted of the area and worked with North Springs Improvement District (NSID) on a model of the drainage system.  NSID was unable to process the permitting for this area, so the City has designated this area as a part of the upcoming citywide Storm Water Master Plan (SWMP).  The SWMP will evaluate the current City storm water level of service and provide recommendations for implementation of policies, strategies, and a prioritized improvement program that addresses the City’s current and future needs.  It is anticipated the SWMP will be complete by the end of Summer 2021.    

PASSIVE PARK ADJACENT TO COVERED BRIDGE PARK

This project is on approximately 2.9 acres along the north side of Holmberg Road and immediately east of Covered Bridge Park.  The area has been overrun by invasive exotic vegetation not native to Florida that hinders healthy growth of native species of trees and foliage.  The first phase of this project, which took place in October 2019, was to remove those invasive species from the area.  During this process, native trees were left and only invasive vegetation was removed. Click here for more information.

Contact Us

  1. Contact

    Enelise Michaels
    City Engineer
    Email

    6600 University Drive
    Parkland, FL 33067

    Ph: (954) 757-4184
    Fax: (954) 753-8838

    Hours


    Monday - Friday
    8:00 A.M. - 5:00 P.M.
For additional information on any project, please contact the City Engineering Department at (954) 7