General Review Process

General Review Process Flow Chart:
1.	Application: Land Use Plan Amendment (County and City Map Amendments Required)
•	Approval Process (Approx. 12 months from time of submission):
a.	Development Review Committee
b.	Planning and Zoning Board
c.	City Commission
d.	Dept. of Economic Opportunity (inclusive of all review agencies including County)
e.	City Commission
2.	Site Plan Application (Approx. 8 months from time of submission)
•	Approval Process:
a.	Development Review Committee
b.	Planning and Zoning Board
c.	City Commission
3.	Plat Note Amendment (approved by City then County)
•	Approval Process: *Additional plat-related requirements may be determined by County via Platting Determination letter
a.	Development Review Committee
b.	Planning and Zoning Board
c.	City Commission
4.	Community Appearance Board Application
•	Approval Process:
a.	Development Review Committee
b.	Planning and Zoning Board
c.	City Commission

1.	Application: Rezoning Application w/ Master Plan Application (if applicable)
•	Approval Process (Approx. 12 months from time of submission): *LUPA + Rezoning second readings are concurrent
a.	Development Review Committee
b.	Planning and Zoning Board
c.	City Commission
d.	City Commission
2.	Site Plan Application (Approx. 8 months from time of submission)
•	Approval Process:
a.	Development Review Committee
b.	Planning and Zoning Board
c.	City Commission
3.	Plat Note Amendment (approved by City then County)
•	Approval Process: *Additional plat-related requirements may be determined by County via Platting Determination letter
a.	Development Review Committee
b.	Planning and Zoning Board
c.	City Commission
4.	Community Appearance Board Application
•	Approval Process:
a.	Development Review Committee
b.	Planning and Zoning Board
c.	City Commission

  • Timeframes are estimates and can vary drastically depending on the applicant’s responsiveness to comments, outside agencies, County review process, and the ultimate development proposal.
  • Additional applications may be required. Graphic for general informative purposes only.
  • Applicant can choose to submit certain applications concurrently as shown or may elect to submit individually.
  • Key:
    • DRC = Development Review Committee
    • PZB = Planning and Zoning Board
    • CC = City Commission
    • DEO = Dept. of Economic Opportunity (inclusive of all review agencies including County)